Procedure Index For IHRG, MSN-99-789

Procedure # Procedure Title Rev Effective Date
100-1 Gas Injection System 1.0 7/00
100-2 PPE Requirements 1.0 7/00
100-3 Operator Logs 4.0 7/00
100-3E Operator Logs 4.0 7/00
100-3Po Operator Logs 4.0 7/00
100-4 Startup and Shut Down Checklist 3.0 7/00
100-5 Unattended Operations 3.0 7/00
100-5E Unattended Operations 3.0 7/00
100-6 Acceptance Testing Document (ATD) 1.0 7/00
200-1 Corrosion Cell Assembly 3.0 7/00
200-2 Furnace Operation 3.0 7/00
200-3 Corrosion Cell Disassembly 2.0 7/00
200-5 Pb - Tapping 4.0 01/01
200-6 NaOH/Pb Corrosion Cell Assembly 4.0 01/01
200-7 Pb and NaOH Sampling 4.0 01/01
300-1 Gas Handling Train 2.0 7/00
300-2 Ventilation 2.0 7/00

Revision Notes

  • Rev. 0.0 was the initial set of procedures submitted to the IHRG committee, on 10/11/99.
  • Rev. 1.0 incorporated the corrections, comments, suggestions, requirements as provided by Gary Roberts and Doug Ardary, completed 10/26/99.
  • Rev. 2.0 incorporated the corrections, comments, suggestion from the second IHRG review held on April 24, 2000 .
  • Rev. 3.0 incorporated corrections based on experimental runs 1 and 2.
  • Rev. 4.0 expanded the use of these SOP's for use in the IHRG Titled: "Clean-up Pb-Bi Coolant" MSN-00-872. Procedure 200-05 was modified (per Gary Roberts's recommendation) during the IHRG. Procedures 200-6 and 200-7 were added and reviewed during the IHRG. Procedure 100-3 were updated to reflect the Mass Spec.