Next Phase: Remedial Planning and Actions

  • United States Army Corps of Engineers (USACE) has procured funding to develop remediation design, plan specifications, and bid documents.
  • Following the design phase, USACE will solicit contract proposals to complete the remediation action.
  • Contract award for plan design should occur in 2021 or early 2022.
  • Funding appropriation of $24 million will be required to perform site remediation.
  • If federal funds are appropriated, remediation of the property would be performed and conclude at the end of calendar year 2023.