Please be advised that work has begun on a Campus Master Plan initiative to make all campus signage cohesive and reflective of UNLV brand standards. The work will take place in phases:
- Phase 1
- Timeline: Started February 28 and will last approximately two weeks
- Work: Includes removing 17 signs that will not be replaced
- Impact: This work may result in impacts to sidewalk access along campus corridors and parking lots.
- Crews will strive to complete work involving concrete removal and jackhammering before 8 a.m. to minimize disruptions to teaching and work environments.
- Phase 2
- Timeline: Will tentatively begin at the end of March and is estimated to be completed by June 2023
- Work: Includes additional sign removal, updating remaining signage and installing new signage.
- Impact:
- A small portion of the Gray Lot will be closed off and used for storing materials
- This work may result in impacts to sidewalk access along campus corridors and parking lots.
- Crews will strive to complete work involving concrete removal and jackhammering before 8 a.m. to minimize disruptions to teaching and work environments.
Thank you for your patience and cooperation as we work to improve the campus experience for faculty, staff, and students.