ISD2
Current and Future Projects
Science and Engineering Building

Project Information

Beginning Construction Date Fall, 2005
Completed Construction Date Spring, 2008
Architect DPHS
Contractor Sletten
Project Budget $113.0 million
Construction Budget $70.4 million
Major Spaces Offices, Classrooms, Laboratories


Exterior Perspectives


Interior Perspectives